Data Acquisition and Processing: 5-7 weeks
Project Website (Manifold IMS) development: 6 weeks
Project report & poster: 4 weeks
Team web page: 4 weeks
17-Sep |
24-Sep |
1-Oct |
8-Oct |
15-Oct |
22-Oct |
29-Oct |
5-Nov |
12-Nov |
19-Nov |
26-Nov |
3-Dec |
Scope & research |
|
|
|
|
|
|
|
|
|
|
|
Proposal |
|
|
|
|
|
|
|
|
|
|
|
|
Data Acquisition |
|
|
|
|
|
|
||||
|
Team Website Development |
|
|
|
|
|
|
||||
|
|
|
|
|
Progress Report |
|
|
|
|
|
|
|
|
|
|
IMS Website Development |
|
|
|||||
|
|
|
|
|
|
|
Final project report/poster |
Project Presentation |