Budget

Data Collection

                        Hours

                        10 hours/week * 5 weeks * 3 analysts +

3 hours/week * 5 weeks * 1 analyst +

5 hours/week * 5 weeks * 1 analyst

Total Hours                                190

Hourly Pay Analysts                   $20

                                                                        Total                 $3,800

Data Analysis

                        Hours

                        10 hours/week *5 weeks * 3 analysts +

                        7 hours/week * 5 weeks *1 analyst +

                        5 hours/week * 5 weeks * 1 analyst

                        Total Hours                                210

                        Hourly Pay Analysts                   $20

                                                                                                Total                 $4,200

System Management

                                    Project Manager

                        Total Hours                                50        

                        Hourly Pay                                $40

                        Pay                                          $2,000

                                    Assistant Project Manager

                        Total Hours                                50

                        Hourly Pay                                $30

                        Pay                                          $1,500             

                                                                                                Total                 $3,500

Web Management

                                    Webmaster

                        Total Hours                                30

                        Hourly Pay                                $25

                        Pay                                          $750

                                                                                                Total                 $750

Equipment Costs (for 10 weeks)

                        Supplies

                        $400/workstation * 5 workstations

                        Maintenance

                        $125/workstation * 5 workstations

                        Depreciation

                        $2000 (total value of equipment)/36(equipment life in months) *

                        2.5 (months equipment will be in exclusive use for the project)

                                                                                                Total                 $2,763.89

Data

                        Purchased Data

                        Software Licenses for 10 weeks

                                    Manifold 8.00 Universal x64

                                    $625/workstation * 5 workstations

                                    ArcView 9

                                    $1500/workstation *4 workstations

                                    ArcInfo

                                    $2500/workstation * 1 workstation

                                                                                                Total                 $12,125

Travel Expenses

                        300 miles at $0.50/mile

                                                                                                Total                 $150

 

TOTAL COSTS                                                                                                 $27,288.89

 

 

 

                                                                                                                                                                                    

                                                                                                                             Go back to aquaKESKA's website!